DOCUMENT TITLE:  EX-10.1: ENGINEERING, PROCUREMENT AND CONSTRUCTION OF A WAVE ENERGY POWER PLANT .
ACTIONS: Here are the clause headings in the document. To view the clause, click the clause heading.To view the full document, click the "View Document" button.

View Document Back
Clause Heading
1 - DEFINITIONS
2 - OBJECT
3 - SCOPE
4 - DOCUMENTATION
5 - INDUSTRIAL INTELLECTUAL PROPERTY
6 - INSPECTIONS AND TESTS
7 - ASSEMBLY AND INSTALLATION OF EQUIPMENT
8.1 - PROTOCOL
8.2 - COMMISSIONING PERIOD
9 - PROVISIONAL ACCEPTANCE
10 - DEFINITIVE ACCEPTANCE
11.1 - MODIFICATIONS AT THE CLIENT'S REQUEST
11.2 - MODIFICATIONS AT THE CONTRACTOR'S REQUEST
12 - CALENDAR AND TIME FOR COMPLETION
12.1 - TIME FOR COMPLETION
12.2 - MONTHLY PROGRESS REPORTS
12.3 - MONITORING AND CONTROL MEETINGS
13.1 - SUSPENSION BY THE CLIENT
13.2 - SUSPENSION BY COURT OR ADMINISTRATIVE AUTHORITY
13.3 - SUSPENSION BY THE CONTRACTOR
13.4 - RECOMMENCEMENT OF WORK
14.1 - CONTRACTOR'S MANPOWER
14.2 - HEALTH AND SAFETY
14.3 - TRAINING
14.4 - COMPLIANCE WITH THE LAW
14.5 - ENVIRONMENTAL PROTECTION
14.6 - EQUIPMENT AND MATERIALS
14.7 - REPLACEMENTS PARTS AND CONSUMABLES
15 - REGULATIONS AND OFFICIAL PROVISIONS CONCERNING EQUIPMENT, LICENCES AND
16.1 - CONTRACTOR'S INSURANCE
a - General Liability, b.
(i) - Industrial Accidents.
(ii) - Motor Vehicle Road Insurance.
16.2 - INSURANCE DOCUMENTS
17 - SUBCONTRACTING
18 - CONTRACT PRICE
19 - TERMS OF PAYMENT AND BILLING
19.1 - SCHEDULE OF MILESTONE
19.2 - COMPLETION OF MILESTONE
(i) - Notice of Approval:
(ii) - Notice of Pending Works:
19.3 - INVOICING
20 - PERFORMANCE BOND/LETTER OF CREDIT
21 - WARRANTIES
21.1 - OWNERSHIP GUARANTEE
21.2 - QUALITY GUARANTEE
21.3 - REPAIR AND REPLACEMENT GUARANTEE
21.4 - POWER OUTPUT GUARANTEE
21.5 - ENERGY PRODUCTION GUARANTEE
21.6 - SPARE PARTS GUARANTEE
21.7 - LIMITATIONS ON GUARANTEES
22 - CLIENT'S OBLIGATIONS
22.1 - ACCESS TO THE SITE AND PERMITS
22.2 - INFORMATION
22.3 - OTHER CLIENT OBLIGATIONS
23 - LIABILITY
24 - FORCE MAJEURE
25 - CHANGES IN LEGISLATION
26 - CLIENT'S AND CONTRACTOR'S REPRESENTATIVES.
27 - ORGANISATION
28 - ASSIGNMENT
29.1 - EXPENSES
29.2 - TAXES
30 - CONFIDENTIALITY
31.1 - TERMINATION BY THE CLIENT:
31.2 - TERMINATION BY THE CONTRACTOR:
31.3 - EFFECTS OF TERMINATION
31.4 - SURVIVABILITY OF CONFIDENTIALITY
32 - DISPUTES
33 - CONTRACTUAL DOCUMENTS AND INTERPRETATION
2 - The Annexes to the Contract
1.0 - BACKGROUND
2.0 - SCOPE
3.1 - PROJECT MANAGEMENT
3.2 - SITE WORK
3.3 - DESIGN ADAPTATION FOR CHOSEN SITE
3.4 - PROCUREMENT, MANUFACTURE, TRANSPORTATION, ASSEMBLY AND TEST
3.5 - SITE PREPARATION
4.3 - Updates
8 - PHOTOGRAPHIC REPORT
1 - GENERAL
2 - BASIC ENGINEERING
3 - DETAILED ENGINEERING
4 - MANUFACTURE
5 - ASSEMBLY
6 - COMMISSIONING
1.0 - SCOPE
2.0 - REFERENCED DOCUMENTS
2.1 - CONTRACTOR DOCUMENTS
2.2 - CLIENT DOCUMENTS
3.1 - GENERAL OVERVIEW
3.2 - TEST PLANNING
3.3 - TEST EXECUTION
3.4 - TEST RESULTS
3.5 - REVIEW OF RESULTS
3.6 - TESTS TO BE INCLUDED