Exhibit 10.1
Confidential Materials omitted and filed separately with the
Securities and Exchange Commission. Asterisks denote omissions.
ENGINEERING, PROCUREMENT AND CONSTRUCTION OF A WAVE ENERGY
POWER PLANT
AT
"PUNTA DEL PESCADOR"
(SANTONA, SPAIN)
<PAGE>
CONTENTS
<TABLE>
<S> <C>
1.
DEFINITIONS............................................................
6
2.
OBJECT.................................................................
13
3.
SCOPE..................................................................
14
4.
DOCUMENTATION..........................................................
14
5. INDUSTRIAL INTELLECTUAL
PROPERTY....................................... 15
6. INSPECTIONS AND
TESTS.................................................. 16
7. ASSEMBLY AND INSTALLATION OF
EQUIPMENT................................. 17
8. COMMISSIONING OF THE
PLANT............................................. 18
8.1
PROTOCOL..........................................................
18
8.2 COMMISSIONING
PERIOD.............................................. 18
9. PROVISIONAL
ACCEPTANCE................................................. 19
10. DEFINITIVE
ACCEPTANCE.................................................. 20
11. MODIFICATIONS OF THE
WORKS............................................. 21
12. CALENDAR AND TIME FOR
COMPLETION....................................... 22
12.1 TIME FOR
COMPLETION............................................... 22
12.2 MONTHLY PROGRESS
REPORTS.......................................... 22
12.3 MONITORING AND CONTROL
MEETINGS................................... 23
13. TEMPORARY SUSPENSION OF
WORK........................................... 23
13.1 SUSPENSION BY THE
CLIENT.......................................... 23
13.2 SUSPENSION BY COURT OR ADMINISTRATIVE
AUTHORITY................... 24
13.3 SUSPENSION BY THE
CONTRACTOR...................................... 24
13.4 RECOMMENCEMENT OF
WORK............................................ 24
14. OTHER OBLIGATIONS OF THE
CONTRACTOR.................................... 25
</TABLE>
<PAGE>
<TABLE>
<S> <C>
14.1 CONTRACTOR'S
MANPOWER............................................. 25
14.2 HEALTH AND
SAFETY................................................. 26
14.3
TRAINING..........................................................
27
14.4 COMPLIANCE WITH THE
LAW........................................... 27
14.5 ENVIRONMENTAL
PROTECTION.......................................... 27
14.6 EQUIPMENT AND
MATERIALS........................................... 28
14.7 REPLACEMENTS PARTS AND
CONSUMABLES................................ 28
15. REGULATIONS AND OFFICIAL PROVISIONS CONCERNING EQUIPMENT
LICENCES AND
PERMITS................................................................
28
16. INSURANCE
16.1 CONTRACTOR'S
INSURANCE............................................ 29
16.2 INSURANCE
DOCUMENTS............................................... 32
17.
SUBCONTRACTING.........................................................
32
18. CONTRACT
PRICE.........................................................
33
19. TERMS OF PAYMENT AND
BILLING........................................... 36
19.1 SCHEDULE OF
MILESTONE............................................. 36
19.2 COMPLETION OF
MILESTONE........................................... 36
19.3
INVOICING.........................................................
36
20. PERFORMANCE
BOND....................................................... 37
21.
WARRANTIES.............................................................
38
21.1 OWNERSHIP
GUARANTEE............................................... 38
21.2 QUALITY
GUARANTEE................................................. 39
21.3 REPAIR AND REPLACEMENT
GUARANTEE.................................. 39
21.4 POWER OUTPUT
GUARANTEE............................................ 40
</TABLE>
<PAGE>
<TABLE>
<S> <C>
21.5 ENERGY PRODUCTION
GUARANTEE....................................... 40
21.6 SPARE PARTS
GUARANTEE............................................. 41
21.7 LIMITATIONS ON
GUARANTEES......................................... 41
22. CLIENT'S
OBLIGATIONS...................................................
41
22.1 ACCESS TO THE SITE AND
PERMITS.................................... 41
22.2
INFORMATION.......................................................
41
22.3 OTHER CLIENT
OBLIGATIONS.......................................... 41
23.
LIABILITY..............................................................
42
24. FORCE
MAJEURE..........................................................
43
25. CHANGES IN
LEGISLATION................................................. 44
26. CLIENT'S AND CONTRACTOR'S REPRESENTATIVES,
NOTICES..................... 44
27.
ORGANISATION...........................................................
45
28.
ASSIGNMENT.............................................................
46
28. TAXES AND
EXPENSES.....................................................
46
28.1.
EXPENSES..........................................................
46
28.2.
TAXES.............................................................
46
29.
CONFIDENTIALITY........................................................
47
30. TERMINATION OF THE
CONTRACT............................................ 49
31.
DISPUTES...............................................................
50
32. CONTRACTUAL DOCUMENTS AND
INTERPRETATION............................... 51
33.
LANGUAGES..............................................................
51
</TABLE>
<PAGE>
ANNEXES
ANNEX I: SCOPE OF AGREEMENT
ANNEX II: SCHEDULE OF WORKS / CALENDAR
ANNEX III: TECHNICAL SPECIFICATIONS OF EQUIPMENT
ANNEX IV: MONTHLY REPORT - CONTENTS
ANNEX V: SCHEDULE OF MILESTONE
ANNEX VI: MODEL OF PROVISIONAL ACCEPTANCE CERTIFICATES
ANNEX VII: MODEL OF DEFINITIVE ACCEPTANCE CERTIFICATE
ANNEX VIII: PERFORMANCE BOND
ANNEX IX: TECHNICAL DOCUMENTATION
ANNEX X: COMMISSIONING PROTOCOL
ANNEX XI: LIST OF SUBCONTRACTORS
ANNEX XII: LIST OF AUTHORIZATIONS AND PERMITS WHICH MUST BE
OBTAINED BY THE
CLIENT AND TIMELINE
ANNEX XIII: LOCATION OF THE PLANT
ANNEX XIV: PREDICTED TECHNICAL PERFORMANCE
<PAGE>
Agreement for the Engineering, Procurement and Construction of a
Wave Energy
Power Plant
Made and entered into in Madrid on July 27, 2006.
BETWEEN
OF THE ONE PART,
IBERDROLA ENERGIAS MARINAS DE CANTABRIA, S.A., with registered
offices in
Santander, Cantabria, calle Amos de Escalante, number 6, 2 B,
represented by Mr.
Roberto Legaz Poignon with Spanish Identification Document number
72013299-T and
Mr. Rafael de Icaza de La Sota with Spanish Identification Document
number
16.035.858-M, in their capacity as Directors, as accredited by
means of the deed
of incorporation of the company signed on this date before the
Notary of Madrid
Mr. Miguel Ruiz-Gallardon Garcia de la Rasilla (the "CLIENT").
AND, OF THE OTHE PART,
OCEAN POWER TECHNOLOGIES LIMITED, a company incorporated in England
and Wales
Company No. 5225532) with its registered office at Warwick
Innovation Centre,
Gallows Hill, Warwick CV34 6UW, United Kingdom, represented by Mr.
Mark Draper,
with UK Passport number 029929083, in his capacity as Director of
the company
(the "CONTRACTOR").
The CLIENT and the CONTRACTOR shall hereinafter be referred to
collectively as
the "PARTIES", and individually as "PARTY".
WHEREAS
I. Whereas, IBERENOVA, OPT, SODERCAN and IDAE have entered in an
agreement
dated on July 2nd, 2004 in respect of a power plant harnessing Wave
Energy
in Cantabria at "Punta del Pescador", near Santona, Spain (the
"SANTONA
WAVE ENERGY AGREEMENT"). Through this agreement, the parties
thereto wanted
to assess the facility and the formalities as well as to confirm
the
viability of the project at the site ("PHASE 1") and set the rules
for
executing such a project of its viability and profitability were
confirmed.
<PAGE>
II. Whereas, TOTAL which was interested in participating in the
Santona Wave
Energy Agreement has joined the Santona Wave Energy Agreement by
signing
its modification on June 17th, 2005.
III. Whereas, in January 2006 the Parties have agreed that Phase 1
had been
completed.
IV. Whereas, Phase 2A of the Santona Wave Energy Project consists
of the
construction of a pilot plant of an initial power of one (01) 40 kW
PB40ES
PowerBuoy, its mooring system, the underwater substation and
submarine
cable both with capacity for energy evacuation of this
PowerBuoy(TM) and
other nine (9) 150kW PB150 PowerBuoys(TM) and all other ancillary
equipment
and services required to provide a complete installation of the
PowerBuoy(TM) 1 x 40KW PB40ES as defined in Annex I.
V. Whereas, the CLIENT resolved to sign this agreement with the
CONTRACTOR,
given that the latter declares to have the necessary skill,
knowledge and
experience for the required works to be executed in Phase 2A.
In virtue of the aforesaid, the Parties hereby execute this
agreement for the
Engineering, Procurement and Construction of a Wave Energy Power
Plant (the
"AGREEMENT"), which will be governed by the following,
CLAUSES
1. DEFINITIONS
1.1 For purposes of this Agreement, the following terms shall have
the meaning
set forth beside each of them (such meanings to be equally
applicable to
both the singular and plural forms of the terms defined).
<TABLE>
<S> <C>
AGREEMENT Means this agreement together with all of
its Annexes.
AGREED PRICE Means the compensation due by the CLIENT to
the CONTRACTOR for the entire and
satisfactory execution of the Works
determined pursuant to Clause 18 of this
Agreement that shall be paid to the
CONTRACTOR according to the Schedule of
</TABLE>
<PAGE>
<TABLE>
<S> <C>
Milestones.
BUSINESS DAY Means any day that is not a Saturday, Sunday
or holiday (whether a national, regional or
local holiday) in Madrid and Cantabria.
CALENDAR Means the timeline for execution of the
Works contained in Annex II.
CERTIFICATE OF COMPLETION OF Means the certificate issued by
the
COMMISSIONING Contractor's Representative which accredits
that the Commissioning Period is finalized
and the Plant is ready for Provisional
Acceptance pursuant to Clause 9 of this
Agreement.
CERTIFICATE OF COMPLETION OF Means the certificate issued by
the
INSTALLATION Contractor's Representative which accredits
that the Plant is ready for commissioning.
CLIENT'S REPRESENTATIVE Means the representative of the Client
as
designated in Clause 26 of this agreement.
COMMISSIONING PERIOD Period commencing upon issue of the
Certificate of Completion of Installation
and finished at the signature of the
Provisional Acceptance Certificate.
CONTRACTOR'S REPRESENTATIVE Means the person appointed by the
CONTRACTOR
in this Agreement under Clause 27.1, who
acts on behalf of the CONTRACTOR.
DAY Means a calendar day.
DEFINITIVE ACCEPTANCE CERTIFICATE Document to be signed by the
Client and the
Contractor after conclusion of Testing
Period in accordance with Clause 10. A draft
of this document is included in Annex VII.
EQUIPMENT Means the equipment and/or materials
supplied by the
</TABLE>
<PAGE>
<TABLE>
<S> <C>
CONTRACTOR and falling within the scope of
this Agreement, as defined in Clause 3 and
the related Annexes.
EURIBOR Means the interest rate applicable among the
banks published in Brussels for the three
months deposits in Euros as it is defined
daily in the Telerate screen, page 248,
11:00 morning time (central Europe time),
the second banking day previous to the
beginning of every period in which the
Automatic Paying System is operative in
Trans European Real Time TARGET. This rate
shall be increased, as the case may be, with
any costs, surcharges, taxes, etc, as duly
supported by documents, which are referred
to in the EURIBOR definition.
FINAL COMMISSIONING PROTOCOL Means the Commissioning Protocol
delivered
by the CONTRACTOR to the CLIENT at least one
month prior to the scheduled date for
commencement of the commissioning.
FORCE MAJEURE Means any event or fact as described in
Clause 24 of this Agreement.
IBERENOVA Means Iberdrola Energias Renovables II S.A.
Sociedad Unipersonal, a company incorporated
and validly existent under the laws of
Spain; registered with the Madrid Commercial
Registry, at Section 8, Page 285710; Tax
Identification Number (C.I.F.) A-83028035,
with registered office at Madrid, Calle
Tomas Redondo, number 1.
IDAE Means Instituto para la Diversificacion y
Ahorro de la Energia, S.A., public entity
ascribed to the Ministry of
</TABLE>
<PAGE>
<TABLE>
<S> <C>
Industry, Tourism and Commerce through the
General Secretary of Energy, with domicile
in Madrid, at Calle Madera number 8 and CIF
number Q 2820009 E.
INDEPENDENT EXPERT Means the qualified specialist appointed by
the School of Industrial Engineers of Madrid
or the Institute of Mechanical Engineers or
Electrical Engineers in London, U.K. upon
request by either Party.
INSURANCE SCHEDULE Means the required policies that the
CONTRACTOR must take out and maintain under
this Agreement.
INTELLECTUAL AND INDUSTRIAL Means all (i) trademarks, trade
names,
PROPERTY Internet domain names, logos, symbols, all
applications and registrations for the
foregoing, and all goodwill associated
therewith and symbolized thereby; (ii)
patents, utility models, registrations,
invention disclosures and applications
therefore, including divisions,
continuations, continuations-in-part and
including renewals, extensions and reissues
and all inventions and discoveries whether
patentable or not; (iii) published and
unpublished works of authorship, whether
copyrightable or not (including databases
and other compilations of information),
Copyrights therein and thereto, and
registrations and applications therefore,
and all renewals, extensions, restorations
and reversions thereof; and (iv) other
industrial and intellectual property or
proprietary rights; concerning the Plant and
the PowerBuoy(TM) system.
KNOW HOW Means all the information, trade secrets,
documents, technical data, technical
knowledge, including processes, schematics,
business methods, formulae, drawings,
prototypes, models, designs, quality control
</TABLE>
<PAGE>
<TABLE>
<S> <C>
systems, quality standards and
specifications developed or acquired by the
CONTRACTOR, presently or in the future,
concerning the Plant and the PowerBuoy(TM)
system, or its design, construction,
commissioning, use, exploitation and
assembling.
MAJOR DEFECTS Means such defects that could affect the
production of energy by the Plant and/or the
safety of the Plant and/or of the people
working therein.
MILESTONE Means the relevant stages of progress of the
Works as described under the Schedule of
Milestones and Calendar.
MINOR DEFECTS Means such material defects that are not
Major Defects.
NOTICE OF APPROVAL Means the document issued by the Client
under Clause 19.2 (i) of this Agreement.
NOTICE OF COMPLETION Means the communication sent by the
Contractor to the Client under clause 19.2
(i) which accredits the completion of a
Milestone.
NOTICE OF PENDING WORKS Means the document issued by the Client
under Clause 19.2(ii) of this Agreement.
OPT Means Ocean Power Technologies, Inc., a
company incorporated and validly existent
under the laws of New Jersey, USA; with
registered office at 1590 Reed Road,
Pennington, NJ, USA.
ORDER FOR CHANGE Means the document signed by both the Client
and the Contractor for a given modification
of the Works under clauses 11.1 or 11.2 of
this Agreement.
PARTIES Means the Client and the Contractor jointly.
</TABLE>
<PAGE>
<TABLE>
<S> <C>
PARTY Means the Client or the Contractor, as the
context may require.
PHASE 1 Means Phase 1 of the Santona Wave Energy
Project as defined in Recital 1 of this
Agreement in which the parties to the
Project have studied and decided about the
viability of the Project at the Site.
PHASE 2A Means Phase 2A of the Santona Wave Energy
Project as defined in Recital IV of this
Agreement, consisting of the design,
manufacture, factory tests, dispatch and
unloading, ex works delivery, assembly and
commissioning of the PowerBuoy(TM) 1 x 40kW
PB40ES, its mooring system, the underwater
substation and submarine cable both with
capacity for energy evacuation of this
PowerBuoy(TM) and other nine (9) 150kW PB150
PowerBuoys(TM) and all other ancillary
equipment and services required to provide a
complete installation of the PowerBuoy(TM) 1
x 40kW PB40ES. All as described in Annex 1.
PHASE 2B Means Phase 2B of the Santona Wave Energy
Project consisting of the design,
manufacture, factory tests, dispatch and
unloading, ex-works delivery, assembly and
commissioning of the nine PowerBuoys(TM) 9 x
150kW PB150, their mooring systems,
submarine cables and all other ancillary
equipment and services required to provide a
complete installation of the PowerBuoys(TM).
PLANT Means the wave power pilot plant
PowerBuoy(TM) 1 x 40kW PB40ES, its mooring
system as well as the underwater substation
and submarine cable (both with capacity for
energy evacuation of this PowerBuoy(TM) and
other nine (9) 150kW PB150 PowerBuoys(TM).
</TABLE>
<PAGE>
<TABLE>
<S> <C>
POWERBUOY(TM) Means the Technology owned by the Contractor.
PRELIMINARY COMMISSIONING Means the Commissioning Protocol attached
to
PROTOCOL the Agreement as Annex X.
PROVISIONAL ACCEPTANCE Document to be signed by the Client and
the
CERTIFICATE OR PAC Contractor to put on record the satisfactory
completion of the Commissioning Protocol,
including all Minor Defects that the
Contractor must remedy within the Testing
Period. A draft of this Document is included
in Annex VI.
SANTONA WAVE ENERGY AGREEMENT Means the agreement signed on July 2,
2004
by OPT, IBERENOVA, SODERCAN, and IDAE, and
modified on June 17, 2005 to include TOTAL
as a party.
SANTONA WAVE ENERGY PROJECT OR Means the pilot project consisting
of a
SWEP power plant harnessing wave energy with an
initial installed capacity of 1.39 MW on the
north coast of Spain based on the
Technology.
SCHEDULE OF MILESTONES Means the schedule describing the
progress
of the Works and the timeline for payment of
the Agreed Price contained in Annex V.
SITE Means the place where the Plant will be
installed located at the coast opposite the
"Punta del Pescador" lighthouse in Santona,
in the Cantabrian region in Spain, as
specified in Annex XIII.
SODERCAN Means Sociedad para el Desarrollo Regional
de Cantabria, S.A., a company incorporated
and validly existent under the laws of Spain
by virtue of its
</TABLE>
<PAGE>
<TABLE>
<S> <C>
incorporation deed granted on December 15,
1984 before the Notary of Santander, Mr.
Jose Antonio Olascoega, with number 1271 of
his public protocol; registered with the
Cantabria Commercial Registry, at Volume
296, Book 101, Sheet 60 and Page S-1751; Tax
Identification Number (C.I.F) A-3904457,
with registered office at Santander, Avenida
de Los Infantes, 32, "Quinta Labat".
SPV Means the public limited company created by
IBERENOVA, IDAE, OPT, SODERCAN and TOTAL for
the construction and operation of the
Santona Wave Project as agreed under the
Santona Wave Energy Agreement.
SUBCONTRACTORS All firms or individuals contracted by the
CONTRACTOR to do part of the Works
contemplated in this Agreement.
TAXES Means any taxes, rates, special levies
("contribuciones especiales"), charges
("exacciones parafiscales") or any other
encumbrance of tax nature, required by any
administrative authority, including
surcharges, interests and penalties.
TECHNICAL DOCUMENTATION Means the documents, workshop plans,
calculations and sketches listed in Annex IX
of this Agreement.
TECHNOLOGY Means the technology for electricity
generation harnessing the energy produced by
the waves called PowerBuoy(TM) system owned
by the CONTRACTOR. In particular, it means
all the Know How and Intellectual and
Industrial Property related to the
PowerBuoy(TM) system, including the moorings
and the
</TABLE>
<PAGE>
<TABLE>
<S> <C>
underwater substation.
TESTING PERIOD Means [**] including [**], plus any
extensions made hereunder. Period commencing
upon signature of the Provisional Acceptance
and finishing at the signature of the
Definitive Acceptance Certificate.
TIME FOR COMPLETION Means the period of time for the
Contractors' completing the assembly,
installation and commissioning of the Plant
according to this Agreement.
TOTAL Means Total Eolica S.A., a company
incorporated and validly existent under the
laws of Spain; registered with the La Coruna
Commercial Registry, at Section 8, Page
25547; Tax Identification Number (C.I.F)
A-15745706, with registered office at
Avenida Fernando de Casas Novoa, number 37,
planta B, 3 degrees A.
WORKS Means all actions, work and services for the
supply, construction and commissioning of
the Plant described in Clause 3 of this
Agreement.
</TABLE>
1.2 Other terms may be defined in other clauses of this
Agreement.
2. OBJECT
2.1 The object of this Agreement is the supply, construction and
commissioning
of the Plant, including the design, manufacture, factory tests,
transport,
dispatch and unloading, ex works delivery, civil works, assembly
and
commissioning and all other ancillary equipment and services
required to
provide a complete installation of the Plant, all as included in
Phase 2A
of the Santona Wave Energy Project and detailed in Annex I.
2.2 The CONTRACTOR undertakes to apply all reasonable efforts to
complete the
supply, construction and commissioning of the Plant within the Time
for
Completion as may be
<PAGE>
adjusted according to the terms of this Agreement and the
Calendar
contained in Annex II.
2.3 The design of the equipment included in Phase 2A that will be
used for
Phase 2B will endeavour to comply also with technical requirements
of Phase
2B equipment.
2.4 The CONTRACTOR shall be responsible for transport of the
Equipment to the
Site and all related expenses, insurance and duties shall be for
the
account of the CONTRACTOR.
2.5 The Equipment supplied hereunder shall generally comply with
the
requirements set forth in Annex III.
2.6 In general, the Works shall be performed in accordance with the
rules of
good practice, with the utmost diligence, care and
professionalism.
3. SCOPE
3.1 The CONTRACTOR shall perform the Works and shall deliver the
Equipment
according to the Technical Documentation detailed in Annex IX.
3.2 The Parties expressly declare that this is an Turnkey Contract,
which means
that the CONTRACTOR will carry out all and any actions or services
that may
be necessary (although not expressly mentioned in the Agreement)
for
completion of the Works to meet the terms of stipulated herein and
those
attached in Annex II, and all applicable standards, regulations and
codes,
shall be deemed included within the scope of this Agreement, even
though
they may not have been expressly mentioned in this Agreement or
Annexes
hereto. Anything without which the Plant would not be in adequate
condition
for normal operation shall be deemed necessary.
3.3 The terminal points of the Plant are the following:
- Submarine cable: submarine cable at the entrance of the
onshore
substation or cable vault if required. Such onshore substation
and/or
cable vault to be supplied by the CLIENT, and no more than
approximately [**] meters from high water level at the beach.
- SCADA System: up to and including the control panel, PLCs and
monitor
within the onshore substation.
<PAGE>
4. DOCUMENTATION
4.1 The CONTRACTOR shall deliver to the CLIENT the Technical
Documentation
listed in Annex IX, within the times and on the terms stipulated
therein
and according to this Clause.
4.2 Upon signing the Provisional Acceptance Certificate, the
CONTRACTOR shall
hand over the "as built" documents of the Equipment in accordance
with
Annex IX, and any other documentation as may be agreed between the
Parties,
all the documents generated during commissioning, including any
modifications based on reasonable written comments made by the
CLIENT and
agreed by the CONTRACTOR on the Provisional Acceptance.
4.3 The CONTRACTOR shall keep at the disposal of the CLIENT a full
set of the
Technical Documentation by number, title, version and date of issue
and all
other documents required from the CONTRACTOR under this
Agreement.
4.4 The CONTRACTOR shall bear all expenses related to the
preparation of the
Technical Documentation.
4.5 For the purposes of Clause 4.1 above, the CONTRACTOR shall
deliver to the
CLIENT a total of three (3) copies and a set on magnetic data
carrier of
the Technical Documentation, which shall be in Spanish or English.
All
technical translations shall be done by professional
translators.
4.6 The CLIENT shall formally provide its approval or any
reasonable comments
to the Technical Documentation within [**] days of receiving the
documents.
If the CLIENT fails to respond without a reasonable justification
within
this period it shall be responsible for any damages or delays
arising
therefrom for the CONTRACTOR, who shall pursue with the Works that
do not
require such approval. The time limit for introducing any
modifications in
response to formal comments that may arise shall be agreed between
the
Parties, but may under no circumstances be more than a further [**]
days.
Approval, the insertion of modifications or lack of response shall
not
exempt the CONTRACTOR from its further obligations and liabilities
under
this Agreement.
5. INDUSTRIAL INTELLECTUAL PROPERTY
<PAGE>
5.1 The CONTRACTOR grants to the CLIENT, who accepts, free of
charge, a
non-exclusive and irrevocable license to use the Technology for (a)
the
construction and commissioning of the Plant by the CONTRACTOR; and
(b) the
future use and exploitation of the Plant subject to the terms of
this
Agreement. The CLIENT shall only use the Technology in connection
with the
Plant.
5.2 The CLIENT acknowledges and agrees that any and all rights to
the
Technology, whether copyrightable or patentable or not, are the
exclusive
property of the CONTRACTOR, or the CONTRACTOR has the right to use
it and
grant licenses, and this Agreement creates on the CLIENT no right
on such
Technology other than the license granted by this Agreement, and
subject to
the terms and restrictions contained hereunder.
5.3 The CONTRACTOR holds all Intellectual and Industrial Property
over its own
Technology.
5.4 The CLIENT, by virtue of this Agreement shall not acquire any
rights over
the trade marks, "know-how", business secrets, trade names,
information,
documentation or any other Intellectual and Industrial Property
used or
developed by the CONTRACTOR in relation to the Technology.
5.5 The CLIENT hereby assigns and agrees to assign to the
CONTRACTOR entire
right, title and interest in and to all inventions, improvements
or
discoveries (whether or not patentable) made, conceived or first
reduced to
practice by the CLIENT based on the Technology.
5.6 The owner of all Intellectual and Industrial Property and Know
How over the
Technology is and shall forever be the CONTRACTOR.
5.7 The CLIENT agrees to promptly disclose the inventions,
improvements and
discoveries specified hereinabove to the CONTRACTOR, and will
assist in
reasonable manner to obtain for the CONTRACTOR's own benefit
patents
thereon at the expense of CONTRACTOR. The CLIENT further agrees
that the
obligations and undertakings stated in this paragraph shall
continue beyond
the termination for any reason of this Agreement but if the CLIENT
is
called upon to render such assistance after such
<PAGE>
termination, then it shall be entitled to a fair and reasonable fee
in
addition to reimbursement of any expenses incurred at the request
of the
CONTRACTOR.
6. INSPECTIONS AND TESTS
6.1 The CONTRACTOR shall allow the CLIENT to make such inspections,
checks,
tests and reports as the Client may consider necessary, during
the
manufacturing, assembly and testing phases, at the factories and
workshops
of both the Contractor and its suppliers and/or Subcontractors.
6.2 The CONTRACTOR will inform the CLIENT in writing with a prior
notice of at
least [**] Business Days, of the dates and places for inspections
and tests
and, particularly, of those that the CLIENT specifically
requested.
6.3 The CLIENT must inform the CONTRACTOR at least [**] Business
Days in
advance of whether it will attend the inspections and tests. If the
CLIENT
is unable to attend, the Contractor will either proceed in his
absence, or
make reasonable effort to reschedule the test, in which case the
CONTRACTOR
may adjust the Calendar accordingly.
6.4 The CLIENT may establish minimum inspection requirements to
check that the
Equipment and/or Works conform to the applicable specifications to
be
agreed with the CONTRACTOR. Should the CLIENT confirm and the
CONTRACTOR
agree, during any inspection or test that the specifications or
standards
have not been met, the CLIENT may freely reject the Equipment
and/or Work
in question at no additional charge or expense and this shall not
be deemed
tantamount to acceptance by the CLIENT of any delay in the Time
for
Completion or alteration of the Agreed Price.
6.5 The inspections or tests by the CLIENT shall not release the
CONTRACTOR
from any of its obligations or liabilities under this Agreement nor
shall
they be deemed equivalent to acceptance of the Equipment
thereof.
6.6 If any fault or defect is discovered during testing and/or
inspection as
contemplated in Clause 6.4, the CONTRACTOR shall be responsible
for
correcting the fault or defect prior to PAC.
<PAGE>
6.7 The CONTRACTOR shall confirm that the manufacturers of the
Equipment comply
with all the requirements of the Agreement and conform to good
practices in
design, engineering and manufacture.
7. ASSEMBLY AND INSTALLATION OF EQUIPMENT
7.1 Upon signature of this Agreement, the CONTRACTOR shall start
each item of
the Works according to the Calendar without the need for
instruction from
the CLIENT, except as outlined in Clause 7.2.
7.2 The Plant shall be installed at the Site once the CLIENT has
given its
written confirmation that the required permits and consents for
installation have been obtained.
7.3 The CLIENT and the CONTRACTOR shall jointly inspect the
Equipment
immediately after its arrival to the dock at [**] or other
reasonable place
and issue a certificate signed by both, specifying the apparent
condition
of the Equipment and any actions that may be necessary to repair or
replace
forthwith any part damaged or lost during transport that may be
detected
during such inspection.
7.4 Inspections by the CLIENT shall not release the CONTRACTOR from
any of its
obligations and liabilities hereunder nor shall they imply
acceptance of
the Plant.
7.5 As soon as the CONTRACTOR considers the assembly and
installation of the
Plant complete, according to the terms of this Agreement, it shall
issue a
Certificate of Completion of Installation indicating that the Plant
is
ready for Commissioning.
8. COMMISSIONING OF THE PLANT
8.1 PROTOCOL
During the commissioning of the Plant, the CLIENT shall appoint an
overseer, who
shall check the correct ap

|